Background
Anderson Acoustics was commissioned by Morgan Sindall to provide acoustic consultancy services from Stage 5 onwards for this new build special school with sixth form, for 70 students aged 11 – 18 with social, emotional and mental health (SEMH).
The primary focus was on optimizing the roof construction to meet rain noise criteria and on exploring other acoustic design elements for potential value engineering opportunities, including room acoustic treatment.
Objectives
- Ensure compliance with acoustic performance standard objectives.
- Identify opportunities for cost savings without compromising quality.
- Address the specific needs of students with special hearing and communication needs (SHCN).
Key Findings
Roof Construction and Rain Noise:
- Simplified and value engineered roof construction whilst still achieving appropriate rain noise standards for students with social, emotional, and mental health needs (SEMH).
Indoor Ambient Noise Levels (IANL):
- Alternative performance standard for indoor ambient noise levels whilst still aligning with recommendations for students with Autism and SEMH needs, appropriate to each use of space.
Sound Insulation:
- Opportunities were identified to reduce sound insulation performance standards in certain areas without affecting compliance with Building Bulletin 93 (BB93).
- Recommendations resulted in cost savings for doors and walls.
- The proposed reverberation time criteria and sound absorption strategy for various spaces were reviewed, with suggestions to incorporate low-frequency bass absorbers in specific rooms to control reverberation time more efficiently whilst value engineering the Stage 4 design solution
Commissioning Testing
Pre-completion testing was conducted to verify compliance with BB93 standards.
- Airborne Sound Insulation: All tested walls met or exceeded the required sound insulation levels.
- Internal Ambient Noise Levels: All tested rooms met the target noise levels, ensuring a conducive learning environment.
- Reverberation Time: All tested rooms met the reverberation time targets, to achieve a suitable acoustic environment given the needs of the students, based on a more efficient and cost effective solution.
Project Progress
The build was completed in 2022. Read more about the project and see images on the Haverstock website here