Background
Anderson Acoustics was appointed by Kier Construction to provide specialist acoustic consultancy across the IOW P22 redevelopment programme at St Mary’s Hospital, Newport. The programme comprised the refurbishment of multiple existing buildings, as well as the construction of new‑build projects delivered within a live hospital environment, including the Health Hub (Project A), Critical Care Unit (Project B), Emergency Department and Fracture Clinic (Project C), Acute 18‑Bed Ward (Project D), and the Community Diagnostic Centre (CDC Wing).
Our role covered acoustic design review, construction‑stage support and acoustic commissioning testing, with performance assessed against HTM 08‑01 guidance and BREEAM Hea 05 requirements.
The Challenge
Each project was delivered within existing hospital structures, with retained fabric, legacy services and operational constraints influencing achievable acoustic performance. Common acoustic challenges included flanking sound transmission via existing steelwork, service penetrations preventing full‑height partitions needed for good standards of acoustic privacy, and ceiling voids shared with retained ductwork.
Clinical requirements introduced further constraints. In patient areas, infection‑control considerations limited the use of acoustic panels and other absorptive finishes, increasing reliance on construction detailing, sound insulation performance and control of building services noise. The challenge was to define suitable acoustic soundproofing standards that were technically justified, achievable on site and appropriate for the use of each space.
Our Approach
A consistent methodology was applied across the programme, using HTM 08‑01 as the primary reference for sound insulation, internal ambient noise levels and room acoustics. Where constraints were identified, alternative performance standards were developed, supported by written technical justification and clear descriptions of the expected level of speech privacy in use.
Regular site inspections were undertaken during construction to review junction detailing, partition head details, service penetrations and ceiling interfaces. This allowed acoustic risks to be identified early and addressed through detailed advice, reducing the likelihood of performance shortfalls at completion.
The Solution
The scope included acoustic design reviews at RIBA Stage 4, Stage 5 site support and a coordinated programme of acoustic commissioning testing. The latter covered airborne sound insulation between noise‑sensitive spaces, internal ambient noise levels from building services, and reverberation time measurements where speech intelligibility was critical.
Across the Health Hub and CDC Wing, the focus was on speech privacy between consultation, treatment and support spaces, alongside reverberation control in offices and shared areas. In the Critical Care Unit and Acute Ward, retained structure and services required careful management of flanking transmission to maintain privacy between patient rooms, staff areas and circulation.
Within the Emergency Department and Fracture Clinic, acoustic performance was managed through a combination of partition derogations, ceiling treatments and crosstalk attenuation to achieve suitable conditions in consultation and treatment rooms despite retained services.
The Outcome
Commissioning testing across Projects A, B, C and D confirmed that the adopted acoustic performance standards were achieved. Internal ambient noise levels from building services complied with HTM 08‑01 criteria in tested spaces.
Sound insulation testing demonstrated that separating constructions met the agreed targets, with minor shortfalls assessed as negligible in acoustic terms and consistent with HTM 08‑01 guidance for refurbished healthcare buildings. Reverberation times in applicable rooms met the adopted criteria, supporting clear communication and functional use.
The verified results enabled the award of the relevant BREEAM Hea 05 acoustic performance credits across the programme.
Conclusion
The IOW P22 programme demonstrates our experience delivering specialist acoustic consultancy across complex healthcare redevelopments. Through detailed design input, technical support during construction and objective testing at completion, compliant and functional acoustic environments were delivered within the constraints of existing hospital infrastructure.
Project Progress
The works were completed in 2024.